The companies belonging to the Association of Industrial Mipymes of Querétaro (AMIQRO) located in the vicinity of the construction zone on Avenida 5 de Febrero are contemplating the possibility of using alternate warehouses in the coming months, so that their freight is not seen affected.
“We think that, if we cannot improve in the next two months, we will have to look for some support warehouses outside the area, but in general, we consider the work to be beneficial, we know that it is necessary, we know that it is a significant problem due to the size of the the intervention".
Check here: Opportunities and risks for a sustained development of industrial investment
Despite the fact that the first days of the week there were operational crises in the five AMIQRO companies that are located in the vicinity of the works that are carried out on Avenida 5 de Febrero, the president of the guild association, José Luis Cámara, considered that it is a matter of time and assimilation to adapt to the situation that the work implies.
“Monday was very chaotic, yesterday we had a crisis of total stagnation at times, it is being reinforced, we are learning together. We, at AMIQRO, have five companies in that section severely affected in the handling of their merchandise.”
The businessman pointed out that the partners agree that the work is necessary, so he called on those who do not have the urgent need to travel through the road to avoid it. He explained that the association he chairs has sought flexibility in shifts, given the circumstances of mobility.
Of interest: Michelin will install an innovative retreading plant in Mexico
Despite the fact that, to date, the damages during the days that the work has been carried out have not been quantified, a possible delay in timely deliveries was previously contemplated, although this does not necessarily represent losses, but percentages of false freights between 1 and two%.
In Solili you can consult industrial buildings available in the Airport and México-Querétaro submarkets